Scope, schedule & cost
CAPM: Certified Associate in Project Management · quick review
Defining what's in and out, turning it into a schedule and a budget, and the estimating techniques behind both.
The rules
- Collect requirements → define scope → create the WBS. The WBS decomposes the work into deliverables down to work packages; the WBS dictionary describes each element.
- Scope baseline = approved scope statement + WBS + WBS dictionary. Validate scope = customer formally accepts deliverables. Control quality = checks they're correct (usually done first).
- Estimating: analogous (top-down, from a similar past project; fast, less accurate), parametric (a unit rate × quantity), bottom-up (sum the work packages; most accurate, slowest), three-point.
- Three-point: triangular = (O + M + P) ÷ 3; beta (PERT) = (O + 4M + P) ÷ 6, with standard deviation ≈ (P − O) ÷ 6.
- Cost baseline includes contingency reserves (for known risks). The project budget = cost baseline + management reserve (for unknown risks, controlled by management).
- Scope creep is uncontrolled growth in scope; the defense is a clear baseline and change control.
Formulas
- Triangular estimate: (O + M + P) ÷ 3
- PERT (beta) estimate: (O + 4M + P) ÷ 6
- PERT standard deviation: (P − O) ÷ 6
- Project budget: Cost baseline + management reserve
Common traps
- Validate scope is about acceptance by the customer; control quality is about correctness. They're different processes.
- Management reserve isn't part of the cost baseline and can't be used without management approval.
- Work not in the WBS is not in scope.
How it's tested
Estimation arithmetic (PERT, triangular), naming the scope artifact, and spotting reserve and baseline confusion.