Study guides / CAPM: Certified Associate in Project Management / Schedule planning & the critical path
Schedule planning & the critical path
CAPM: Certified Associate in Project Management · quick review
Building a network schedule: sequencing activities, finding the critical path and float, and compressing the schedule when it's too long.
The rules
- Steps: define activities → sequence them → estimate durations → develop the schedule. The precedence diagramming method shows activities as boxes with dependencies.
- Dependency types: finish-to-start (most common), start-to-start, finish-to-finish, start-to-finish (rare). A lead overlaps the next activity; a lag adds a wait.
- Dependencies can be mandatory (hard logic), discretionary (preferred logic), external or internal.
- The critical path is the longest path through the network; it sets the shortest possible duration. Critical activities normally have zero total float.
- Total float = LS − ES = LF − EF (how long an activity can slip without delaying the project). Free float = how long it can slip without delaying the next activity.
- Crashing adds resources to critical activities (costs more). Fast tracking overlaps activities (adds risk and rework). Resource leveling can lengthen the critical path; resource smoothing works only within float.
Formulas
- Total float: LS − ES or LF − EF
- Forward pass: EF = ES + duration (− 1 if counting from day 1)
Common traps
- Compressing an activity that isn't on the critical path doesn't shorten the project.
- Shortening the critical path can create a new critical path.
- Duration is working time; elapsed time includes weekends and waits.
How it's tested
Finding the critical path and float from a small network, and picking the right compression technique.
Practise it
The full lesson, worked examples and practice questions are in Tickmark, where every answer choice is explained.