Resources & procurement
CAPM: Certified Associate in Project Management · quick review
Getting and leading the people, and buying what the project can't make: team development, conflict, motivation, responsibility charts and contract types.
The rules
- RACI (Responsible, Accountable, Consulted, Informed): exactly one Accountable per activity. It's a type of responsibility assignment matrix (RAM).
- Tuckman's stages: forming → storming → norming → performing → adjourning. Teams can slide back when members change.
- Conflict approaches: collaborate/problem solve (win-win, best long term), compromise/reconcile, smooth/accommodate, force/direct, withdraw/avoid. Address conflict early and privately.
- Motivation theories: Maslow (hierarchy of needs), Herzberg (hygiene factors prevent dissatisfaction; motivators such as achievement drive satisfaction), McGregor (Theory X distrust, Theory Y trust).
- Make-or-buy analysis decides what to procure. Documents: statement of work, RFP (proposals, when solutions differ), RFQ (price quotes for defined items), RFI (information).
- Contract types, from most buyer risk to least: cost-reimbursable (CPFF, CPIF, CPAF) → time and materials → fixed price (FPIF, FP-EPA, FFP).
Common traps
- Pay and working conditions are hygiene factors (Herzberg): they stop dissatisfaction but don't motivate on their own.
- Forcing resolves a conflict fast but rarely lasts; collaborating is the preferred long-term approach.
- Time and materials contracts suit small or unclear work, but costs can grow without a not-to-exceed limit.
How it's tested
Team stage and conflict-style identification, RACI rules, and which contract type shifts which risk.