Kanban, lean & flow
CAPM: Certified Associate in Project Management · quick review
Managing the flow of work continuously: visual boards, work-in-progress limits, lean waste reduction and flow metrics.
The rules
- Kanban practices: visualize the workflow, limit work in progress (WIP), manage flow, make policies explicit, and improve collaboratively. Work is pulled when there's capacity.
- Lead time: from request to delivery. Cycle time: from starting work to finishing it. Throughput: items finished per period.
- Little's law: average WIP = throughput × average lead time. Lower WIP means shorter lead times.
- Lean aims to maximize value and eliminate waste, such as partially done work, extra features, handoffs, waiting, task switching and defects.
- Value stream mapping shows every step from request to delivery to find delays and waste.
- Information radiators (big visible charts and boards) keep progress transparent to everyone.
Formulas
- Little's law: WIP = throughput × lead time
Common traps
- Starting more work doesn't speed delivery; it lengthens queues.
- Kanban has no required iterations or roles; it can start from the current process.
How it's tested
Diagnosing a flow problem on a board and applying WIP limits or lean waste ideas.