Study guides / CAPM: Certified Associate in Project Management / Iteration planning & estimation
Iteration planning & estimation
CAPM: Certified Associate in Project Management · quick review
Planning work in iterations: user stories, relative sizing, velocity-based forecasting and the charts that track progress.
The rules
- User story format: "As a [role], I want [capability] so that [benefit]." Good stories are INVEST: independent, negotiable, valuable, estimable, small, testable. Each has acceptance criteria.
- Story points are relative sizes, often on a Fibonacci-like scale; planning poker reaches consensus and exposes different assumptions.
- Velocity is the points a team completes per iteration; use the team's own average to forecast. Velocity isn't comparable between teams.
- Burndown chart: work remaining over time. Burnup chart: work completed and total scope, which shows scope changes.
- A spike is a timeboxed investigation to reduce uncertainty. The definition of ready is a team's check that a story is clear enough to plan.
- Release planning sets roughly which features land in which iterations; the MVP (minimum viable product) is the smallest release that tests the idea with real users.
Formulas
- Iterations remaining: Remaining story points ÷ average velocity
Common traps
- Raising velocity isn't a goal in itself; pushing it leads to inflated estimates.
- Story points measure relative effort and complexity, not hours.
How it's tested
Velocity forecasts, reading burndown and burnup charts, and story quality.