Earned value & cost control
CAPM: Certified Associate in Project Management · quick review
Measuring cost and schedule performance with earned value: the three base numbers, the variances and indexes, and the forecasts.
The rules
- PV (planned value): the budgeted cost of work scheduled. EV (earned value): the budgeted cost of work actually done. AC (actual cost): what the work done actually cost. BAC: total budget.
- Variances: CV = EV − AC; SV = EV − PV. Negative = over budget or behind schedule.
- Indexes: CPI = EV ÷ AC; SPI = EV ÷ PV. Above 1 = good; below 1 = bad.
- Forecasts: EAC = BAC ÷ CPI (if current performance continues); EAC = AC + (BAC − EV) if the variance was a one-off; ETC = EAC − AC; VAC = BAC − EAC.
- TCPI = (BAC − EV) ÷ (BAC − AC): the efficiency needed on the remaining work to finish on budget.
Formulas
- Cost variance: CV = EV − AC
- Schedule variance: SV = EV − PV
- Cost performance index: CPI = EV ÷ AC
- Schedule performance index: SPI = EV ÷ PV
- Estimate at completion (typical): EAC = BAC ÷ CPI
- Estimate to complete: ETC = EAC − AC
- Variance at completion: VAC = BAC − EAC
- To-complete performance index: TCPI = (BAC − EV) ÷ (BAC − AC)
Common traps
- Every formula starts with EV. Mixing up PV and AC is the most common error.
- A CPI of 0.8 means $0.80 of value for each $1 spent: the project is over budget.
- At the end of a project, SV becomes zero and SPI 1.0 even if it finished late, because EV = PV = BAC.
How it's tested
Calculations from given PV, EV, AC and BAC, then interpreting whether the project is ahead or behind.