Study guides / CAPM: Certified Associate in Project Management / Documentation & controls
Documentation & controls
CAPM: Certified Associate in Project Management · quick review
The plans, logs and baselines a predictive project keeps, and the controls that keep them accurate: version control, configuration management and change logs.
The rules
- The project management plan (subsidiary plans + baselines) is controlled: changes need approval. Project documents (logs, registers, estimates) are updated as needed.
- Configuration management identifies the approved version of each deliverable and document and controls updates to it; version control tracks revisions.
- The change log records every change request and its status; the issue log tracks problems happening now; the risk register tracks what might happen.
- Work performance data (raw observations) → work performance information (analyzed against the plan) → work performance reports (for decisions).
- Milestones have zero duration and mark significant points; a milestone list and Gantt chart communicate the schedule.
Common traps
- An issue is happening now; a risk might happen. They go in different logs.
- Raw data isn't information until it's compared with the plan.
How it's tested
Which document holds which information, and what control prevents a described documentation failure.