Study guides / CAPM: Certified Associate in Project Management / Communications & stakeholders
Communications & stakeholders
CAPM: Certified Associate in Project Management · quick review
Finding everyone the project affects, understanding their power and interest, and planning the right communication for each.
The rules
- Identify stakeholders early and keep the stakeholder register current; stakeholders change during the project.
- Power/interest grid: high power, high interest → manage closely; high power, low interest → keep satisfied; low power, high interest → keep informed; low power, low interest → monitor.
- Stakeholder engagement assessment matrix compares current (C) and desired (D) engagement: unaware, resistant, neutral, supportive, leading.
- Methods: interactive (meetings, calls; best for complex or sensitive issues), push (email, memos, reports), pull (portals, knowledge bases; large audiences who look it up).
- Communication channels = n(n − 1) ÷ 2. Adding people increases complexity quickly.
- The communications management plan sets who needs what information, when, how, and from whom.
Formulas
- Communication channels: n(n − 1) ÷ 2
Common traps
- Ask how many channels were added versus the new total; they're different answers.
- Sensitive or complex news (a major delay, a conflict) calls for interactive, face-to-face communication, not email.
- Ignoring a low-interest, high-power stakeholder is a classic cause of late surprises.
How it's tested
Grid placement, choosing a communication method, and channel counts.